Levels of Front-End Engineering

 

Rough Order of Magnitude
Quotation
(+/- 50%)

Refined Quotation
(+15%/-5%)

Fixed Bid Quotation
(+/-0%)

Advantages

  • Least cost method for approximate project value
  • Project scope 90% defined.

  • Included contingency minimized as most "Unknowns" have been turned into "Knowns."

  • Approximately 10% of design engineering completed.

  • Front End Engineering value credited against Fixed Bid Quotation value.
  • Project Timeline defined and Long Lead items identified.
  • Project scope, timeline and approach totally defined and solidified.


  • No future financial risk to client if project scope does not change.


  • No surprises later because proper due diligence was funded to arrive at the project value.


  • Included contingency minimized as "Unknowns" have been turned into "Knowns".


  • Approximately 15% of design engineering completed. Front End Engineering value issued as credit against Fixed Bid Quotation value.
  • Disadvantages

  • Difficult to fund due to lack of accurate cost


  • Large $$ variability from vendors - Who do you believe?
  • Typical Uses

  • Placement of project in next year's capital budget
  • Best value approach to arrive at an accurate project estimate
  • Appropriation of capital funds.
  • Engineering

  • No significant engineering done
  • Identify Line Rate, Identify Major pieces of Equipment.

  • Define Line Control/Automation Strategy.

  • Identify major civil/facility upgrades/changes required
  • Major and Minor pieces of equipment identified.

  • Control/Automation Strategy Identified, Identify major civil/facility upgrades/changes required.

  • Power and Air Consumption requirements identified.


  • Performance criteria identified.

  • Peer design review conducted.
  • Programming & Integration

  • Compare to projects of similar magnitude
  • Programming hours estimated based on Line Control Strategy
  • Programming hours estimated based on Line Control Strategy
  • Equipment Pricing

  • Compare to projects of similar magnitude
  • Use recent pricing for standard packaging equipment (Conveyors, Fillers, Packers, Tapers, etc.) and secure current pricing for complex and specialty equipment
  • Accurate current pricing for all major and minor equipment
  • Project Timing

  • Compare to projects of similar magnitude
  • Create project timeline based on major pieces of equipment delivery estimates
  • Identify all equipment delivery dates.

  • Project Timeline to include complete project execution dates.
  • Line Layout

  • No drawings developed.
  • Preliminary layout drawing developed.
  • Preliminary layout and equipment drawings developed.
  • EPIC Fabrication

  • Compare to projects of similar magnitude.
  • Fabrication hours calculated based upon preliminary layout
  • Mechanical and electrical labor hours calculated based upon preliminary layout.

  • Peer estimate review to confirm accuracy and thoroughness.
  • Acceptance Testing

  • No FAT plan developed or accounted for.
  • Use preliminary layout and Controls Strategy to estimate FAT effort required.
  • Use preliminary layout and Controls Strategy to estimate FAT effort required.
  • Field Installation

  • Compare to projects of similar magnitude.
  • Develop internal estimates for mechanical and electrical installation scope
  • Secure firm bids from subcontractors for civil, utilities, mechanical and electrical installation scope.
  • Start-up & Commissioning

  • No Check-out or Commissioning plan included.
  • Use preliminary layout and Controls Strategy to estimate Field Checkout.
  • Use preliminary layout and Controls Strategy to estimate Field Checkout.
  • Develop basic Commissioning Plan with customer.
  • Click to return to Front-End Engineering

    Click to view Front-End Engineering Deliverables

     

    Case-Study

    View Packaging Lines Case Studies…

    Find case studies about different project applications EPIC has completed and specific unit operations within each project.

    Blog

    Click here to view our blog…

    Our blog features topics on industry, engineering tips and company updates.

    Press Release

    View our latest press releases…

    Stay up-to-date on what is happening at EPIC. You will find press releases on packaging line systems being delivered to clients, awards won by EPIC and new employees hired.

    Free Newsletter

    Stay up-to-date on current industry news and trends by subscribing to our packaging systems newsletter. Our newsletters are sent out semi-annually and cover interesting news, trends, industry topics as well as updates on EPIC Systems.